2023: the last match and the first cranes
The old Camp Nou's last match before the works was against Mallorca on 28 May 2023. Work on the stadium, part of the club's Espai Barça project, began on 1 June 2023.

2023–2025: two seasons on Montjuïc
Barça played the 2023–24 and 2024–25 seasons at the Estadi Olímpic Lluís Companys on Montjuïc, the 1992 Olympic stadium, and opened 2025–26 at the Johan Cruyff Stadium and the Olímpic while the new bowl went up.

22 November 2025: home again
The first competitive match at the rebuilt stadium was LaLiga against Athletic Club on Saturday 22 November 2025. Barça won 4–0, with two goals from Ferran Torres and one each from Robert Lewandowski and Fermín López, two and a half years after the last match on Montjuïc ended the exile.

2026: more seats, not the top tier
The city approved the next phase of opening in March 2026, including the north end. In September 2026 SPORT reported, and Barça Universal relayed, that the club had decided to keep the whole third tier closed for the 2026–27 season, after the city required a single licence for that section and a late-season opening proved too costly; the tier is expected to open once the roof is built. VIP boxes are still being added during the season.
2027: the roof, and maybe Montjuïc again
Roof installation is due to start in June 2027. In July 2026 the newspaper Ara reported that the club had booked the Estadi Olímpic until December 2027 for the first months of the 2027–28 season, pending official confirmation; official estimates put the roof work at up to five months, engineers at about seven. If that plan holds, the last listed home match of this season, Málaga on 23 May 2027, is the last at Camp Nou before the roof.

What it means for a visitor this season
- Every seat on sale is in the first or second tier.
- Access routes around the stadium are narrower and change as work moves; follow the signs.
- Parking is reduced; the club recommends the metro and tram.
- The stadium has no roof yet: bring a layer and something for rain in winter.
- The museum viewpoint looks over the construction, which makes a visit this season different from any other.
Where sources disagree
The club has not published a single dated timeline for the remaining works. The dates for the third tier and the roof come from reporting in SPORT, Ara and Football Ground Guide, and they have moved more than once. This page will follow the club's announcements as they come.